New condo or home delayed? Tarion delay compensation, the outside date and the right to terminate

If your builder misses your occupancy or closing date, Tarion's pages set out what you can claim and how long you have.

BuyingCondosOntario

Photo: KENSET on Unsplash

← All Perspectives

The short version

  • Delay compensation is payable up to a maximum of $7,500.
  • Living expenses are $150 per day of delay, and receipts are not required for that part.
  • Other costs, such as extra moving or storage, need receipts.

What Tarion says you can claim

Tarion publishes separate pages for condo units (occupancy dates) and for freehold homes and other contract homes (closing dates). Both say delay compensation is payable up to a maximum of $7,500.

$7,500maximum delay compensation
$150per day of delay for living expenses
$1,500if the builder gives under 10 days' notice of the delay

The condo page says $150 per day is paid until the Delayed Occupancy Date or until you terminate, and receipts for living expenses are not required. Costs caused by the delay, such as extra moving or storage, are also payable, but receipts are required.

If the builder does not give 10 days' notice of a delay, Tarion says you get $1,500, which is $150 for each of 10 days. If you terminate because of the delay, you are also entitled to a full refund of money paid, including deposits, extras and upgrades, plus interest.

Sources: Tarion, Condo units: coverage for occupancy dates, delays and cancellations; Tarion, Freehold and contract: coverage for closing dates and delays

The dates that matter

In a condo purchase, the Firm Occupancy Date is the date the builder commits to. If it is missed, the builder must set a Delayed Occupancy Date and compensation applies. The Outside Occupancy Date is the latest date the builder agreed to provide occupancy, agreed at signing. Tarion says you have 30 days after the Outside Occupancy Date to terminate.

For a freehold home with a Firm Closing Date, Tarion says the Outside Closing Date is 365 days after the Firm Closing Date, and it is the latest closing date available to the builder (the rule differs where tentative closing dates are used, so read your addendum). If the home is not complete by then, you have 30 days to terminate.

Tarion also says at least 90 days' written notice is generally needed to change a closing date, and that a change by mutual agreement can mean you give up compensation. The builder can extend dates for unavoidable delays without compensation, but must tell you at the start, estimate the length and give written notice when it ends.

30days

The window to terminate after the Outside Occupancy Date (condo) or the Outside Closing Date (freehold), per Tarion.

Sources: Tarion, Condo units: coverage for occupancy dates, delays and cancellations; Tarion, Freehold and contract: coverage for closing dates and delays

Claim deadlines

Tarion says you claim from the builder first, within 180 days of your occupancy or closing date, or of the date you terminate. If the builder does not pay, or you cannot agree on the amount, you claim from Tarion during the first year of possession, or up to 365 days after termination.

Claims use the Delayed Closing/Occupancy Claim Form on MyHome, Tarion's online service for homeowners.

Sources: Tarion, Condo units: coverage for occupancy dates, delays and cancellations; Tarion, Freehold and contract: coverage for closing dates and delays

What to check and keep

  • The exact dates in your purchase agreement and its Tarion addendum: Firm, Tentative and Outside dates.
  • Each written notice from the builder, with the date you received it.
  • Receipts for moving, storage and other direct costs caused by the delay.
  • The calendar dates of your 180-day and 30-day windows once a date is missed.
  • Before you sign any amendment that changes a date, whether it affects compensation.

Tarion's own pages say the addendum attached to your purchase agreement governs your specific rights and suggest speaking with a lawyer if you are unsure. A lawyer can read the addendum with you before you sign anything the builder sends.

This is general information based on public sources, not legal advice. Your own documents and a lawyer you consult decide how the rules apply to your unit.

Sources: Tarion, Condo units: coverage for occupancy dates, delays and cancellations; Tarion, Freehold and contract: coverage for closing dates and delays

This is general information, not legal advice.