The situation
Camila ran a small commercial supply business out of Ancaster, sourcing and delivering industrial HVAC components to contractors across the region. Over a decade she had built a reputation for reliable equipment and on-time delivery, and most of her work came through repeat relationships with a handful of mechanical contractors rather than public bids. One of her regular clients had installed a rooftop unit she supplied at a mid-sized commercial building. Eight months after installation, the building's owner discovered water damage traced to a failed component in the unit, and the repair and remediation bill came to roughly $410,000, covering drywall, insulation, and mould remediation across two floors below the mechanical room.
The building owner sued everyone connected to the project: the general contractor, the mechanical contractor who installed the unit, and Camila's supply business, which had sold and delivered the equipment. The claim against Camila's company alone sought damages of roughly $600,000, reflecting the building owner's position that the equipment itself was defective and that her business, as supplier, bore responsibility alongside the installer.
Camila had never been named in a lawsuit before. She had liability insurance through her business, but the policy had a deductible high enough that a prolonged fight would still cost her real money, and the claim threatened both her savings and her ability to keep working with the contractor who had brought her the business in the first place. She came to us within two weeks of being served, worried mainly about the time and legal cost of defending a claim she believed was fundamentally about someone else's workmanship.
The legal problem
A claim like this usually turns on one question: whose conduct actually caused the failure. In a multi-party construction and supply dispute, each defendant tends to point at the others, and without early clarity, all of them can end up litigating for years before anyone determines who was really at fault. The general contractor blamed the mechanical contractor's installation crew. The mechanical contractor, whose lead installer was a man named Simran, pointed back at the equipment itself, arguing the unit's drainage fitting was undersized for the load. Camila's business sat in the middle, blamed by two parties who had every incentive to blame anyone but themselves.
The building owner's statement of claim alleged that the rooftop unit itself was defective when delivered. If that were true, Camila's business could face liability under general principles of negligence and, depending on the terms of sale, potentially a claim for breach of an implied warranty that goods sold are reasonably fit for their intended purpose. But Camila's own review of her supply and delivery records showed the unit had passed the manufacturer's standard quality checks before it left her warehouse, and she suspected the failure had more to do with how the unit was installed and connected to the building's drainage system than with anything wrong with the equipment itself.
The difficulty was that suspicion is not evidence. Without a technical assessment of what actually failed and why, the case would proceed on competing narratives, with every party's lawyer arguing plausibility rather than fact. That kind of dispute is expensive to litigate because so much of the early work — document exchange (called documentary discovery, where each side must produce relevant records) and questioning of witnesses under oath (called discovery) — happens before anyone commissions the one piece of evidence that would actually resolve the question: an independent opinion from someone qualified to say what caused the failure. Left to run its normal course, the case could easily have consumed two or three years and a substantial share of Camila's insurance limits before that question was ever properly answered.
What we did
- Reviewed the claim and Camila's records before filing a defence. Our team examined the statement of claim alongside Camila's purchase orders, delivery records, and the manufacturer's specifications for the unit, to understand exactly what had been supplied and what commitments, if any, had been made about its performance once installed. We also flagged the delivery inspection log as a document worth preserving carefully, since it would matter later.
- Filed a statement of defence and crossclaim. The defence denied that the equipment was defective and put the building owner to strict proof of causation. Alongside it, we filed a crossclaim against the mechanical contractor whose crew, led by Simran, had performed the installation, preserving Camila's ability to seek contribution from the installer if the court ultimately found shared or sole responsibility on their side.
- Retained an independent professional engineer early, rather than waiting for trial. Most litigation strategies leave expert evidence until the case is well advanced, often after a full year or more of document exchange. We took the less common approach of commissioning a standard-of-care opinion from a professional engineer, Valentina, at the outset, while the failed component and installation were still physically available for inspection before repairs disturbed the evidence. Valentina's mandate was narrow and specific: examine the failed unit and its connections, and give an opinion on whether the failure was more consistent with a manufacturing or supply defect, or with an installation error.
- Shared the opinion with opposing counsel once it was in hand. Valentina's report concluded that the unit's internal components met the applicable manufacturing standard, and that the water intrusion was consistent with an improperly sealed connection at the point where the installation crew had tied the unit into the building's drainage line — a workmanship issue, not a supply defect. We disclosed the report to all parties rather than holding it back for trial, on the view that a strong, independent finding works harder for a client when the other side has time to absorb it and adjust their position.
- Used the opinion to reframe settlement discussions. With a credible, independent technical opinion pointing away from Camila's business, we pressed for her dismissal from the claim, or at minimum a resolution that reflected her business's minimal exposure relative to the installer, and made clear Camila was prepared to let the report speak for itself at trial if a fair resolution could not be reached.
The outcome
Valentina's opinion changed the shape of the case. The building owner's own insurer commissioned a second, independent review of the report and largely agreed with its conclusions. Facing a credible finding that pointed toward the mechanical contractor's workmanship rather than the supplied equipment, the building owner's counsel narrowed the claim against Camila's business substantially rather than continuing to pursue the full $600,000.
The parties reached a resolution before examinations for discovery were completed and well before any trial date was scheduled. Camila's business contributed a modest amount, covered entirely by her insurer within the policy limits, reflecting a small residual uncertainty about delivery handling rather than any finding of fault in the equipment itself. The bulk of the liability shifted to the mechanical contractor's own insurer under a separate settlement. Camila's crossclaim was withdrawn as part of the overall resolution, since it had done its job of keeping her position protected while the real dispute sorted itself out.
The case never reached trial. From the point the engineer's report was disclosed to final resolution took a little under a year — fast by litigation standards, and far faster than the two to three years a fully litigated construction dispute of this size often takes. Camila's ongoing relationship with the mechanical contractor survived intact, since the dispute resolved on the facts rather than through a bitter, prolonged fight where every party tried to shift blame onto every other party in open court.
What you can learn from this
- In multi-party disputes, get independent expert evidence on causation early rather than waiting until trial preparation — it can reshape the entire negotiation, not just support the eventual trial.
- A narrow, well-defined expert mandate produces a more useful opinion than a broad one. Asking one specific technical question gets a clearer answer than asking an expert to review the whole dispute.
- Filing a crossclaim against a co-defendant preserves your right to seek contribution if liability shifts, and costs little to file — it is a form of insurance while the facts are still being sorted out.
- Disclosing a favourable expert report to the other side, rather than saving it for trial, can accelerate settlement by giving everyone a shared, credible basis for evaluating the case.
- A business's liability insurance deductible is a real cost even when a claim eventually goes nowhere — understanding it early helps set realistic expectations for what a dispute will cost regardless of outcome.
This is a litigation problem we handle
Start a file online — flat, published fees, reviewed by a licensed lawyer before a dollar is owed.