TREADSTONE LAW · ONTARIO · DIGITAL LEGAL SERVICES · EST. MMXXI ·TSL
Home/Case Studies/Litigation
№ 10 Case Study — Litigation

Three Trades, One Insolvent Builder: Coordinating Liens in Midland

When a Midland general contractor stopped paying, a husband-and-wife painting business and a fellow subcontractor learned that acting fast and acting together was the only way to get paid.

Litigation5 min readMidland, OntarioConstruction liens
All Litigation case studies
ClientChantal and Rejean, who run a small drywall and painting subcontracting business in Midland
The issueGeneral contractor stopped paying subcontractors and became insolvent mid-project
ServiceConstruction lien registration and enforcement, coordinated across trades
ResolutionRecovered most of what was owed from the holdback, working alongside another unpaid subcontractor

The situation

Chantal and Rejean built their drywall and painting business slowly. Chantal had spent years working as a personal support worker before the couple decided to go out on their own, taking on residential jobs around Midland one at a time until the business could support them both. By the time a general contractor hired them for the drywall, taping and painting package on a six-unit residential build, it was the largest contract they had ever signed: roughly $28,000 for their portion of the work.

The job went smoothly for the first few months. Chantal and Rejean submitted invoices as milestones were completed, and payments came in, though a little slower each time. Then the payments stopped altogether. Two invoices, totalling about $19,000, sat unpaid. When Rejean called the contractor's office, the calls stopped being returned. A supplier they knew mentioned that other trades on the same project were having the same problem.

One of those trades was Nadia, who ran a small electrical subcontracting business and was owed roughly $14,000 for wiring rough-in work on the same six units. Nadia's partner worked as an early childhood educator, and that second income was the only thing keeping their household steady while the business waited on a payment that showed no sign of coming. Within a few weeks, word around the project was that the general contractor was in serious financial trouble and might not finish the build at all.

The legal problem

Chantal and Rejean had no direct contract with the property owner who commissioned the building; their contract was with the general contractor, who had gone quiet. In Ontario, unpaid subcontractors in that position are not without options. The Construction Act gives contractors and subcontractors who supply labour or materials to an improvement the right to register a construction lien against the title of the property itself, even without a direct contract with the owner. But that right comes with strict, unforgiving deadlines, and once they expire, they cannot be revived.

A lien has to be preserved, meaning registered on title, within a set window that runs from the last day the claimant supplied services or materials to the project. If that window is missed, the lien right is gone permanently, regardless of how legitimate the debt is. Once preserved, a lien then has to be perfected within a further deadline, which means starting a court action and registering a certificate of action on title. Miss that second deadline and the preserved lien expires too.

There was a second complication. Ontario law requires owners and contractors to hold back a percentage of the contract price on every construction project, specifically to protect subcontractors in exactly this situation. That holdback fund is where lien claims ultimately get paid from, but it is finite. If several trades are chasing the same limited holdback, and one moves faster or louder than the others, the ones who wait can find there is little left by the time they act. With the general contractor's financial trouble becoming public and a mortgage lender also holding registered security against the property, Chantal and Rejean were racing against both a legal deadline and a shrinking pool of money.

What we did

  1. Confirmed the deadline before anything else. The first call was to establish exactly when Chantal and Rejean last supplied services to the project, since that date sets the countdown for preserving a lien. Missing it by even a day would have ended their claim, so this was treated as the single most urgent fact in the file.
  2. Registered the lien against the property. We prepared and registered a construction lien on title for the full amount owing, plus the modest costs the Construction Act allows a claimant to add. Registering the lien puts the world, including the mortgage lender, on notice that Chantal and Rejean's business has a claim against the property.
  3. Reached out to Nadia's business the same week. Once it was clear other trades were affected, we contacted Nadia to coordinate rather than compete. Multiple lien claimants drawing on the same holdback are far better served comparing notes than moving in isolation, since a shared understanding of who is owed what, and when everyone's deadlines fall, avoids a scramble that benefits no one but the insolvent contractor.
  4. Perfected the lien by starting a Small Claims Court action. Because the amount owing fell within the Small Claims Court's monetary jurisdiction, we started the action there rather than in the Superior Court, keeping the process faster and less costly than a full lien action would otherwise be. A certificate of action was registered on title within the required window to keep the lien alive.
  5. Pressed the owner and the holdback directly. With the lien perfected, we corresponded directly with the property owner and their lawyer, setting out the holdback obligation and Chantal and Rejean's claim against it. We did the same on Nadia's file, so the owner was dealing with a coordinated, clearly documented position from both trades rather than piecemeal demands.
  6. Negotiated a proportional settlement from the holdback. Once it was clear the general contractor would not be paying anyone directly, the realistic path to recovery was the holdback fund itself. We negotiated with the owner's lawyer for both files together, which avoided a costly race to judgment and got money moving months sooner than a contested trial would have allowed.

The outcome

Chantal and Rejean recovered the large majority of the roughly $19,000 they were owed, paid out of the holdback fund a few months after the lien was registered, without needing to take the Small Claims Court action to trial. Nadia's business recovered a similar proportion of its roughly $14,000 claim on the same timeline. Neither business recovered every dollar of interest and cost they were technically entitled to claim, but both avoided the far worse outcome of an expired lien and an unenforceable debt against an insolvent contractor with nothing left to collect from directly.

The coordination mattered as much as the paperwork. Acting together meant the owner faced two organized, properly perfected claims instead of a disorganized scramble among several trades, and it meant Chantal and Rejean's business was never at risk of being pushed to the back of the line by a faster-moving lienholder. For a small business running on tight margins, getting paid within months rather than waiting through a drawn-out insolvency process made the difference between absorbing a setback and facing a much deeper cash-flow crisis.

What you can learn from this

  • The deadline to register a construction lien in Ontario runs from the last day you supplied labour or materials, not from the day you noticed you weren't being paid. Track that date on every project, and treat any sign of a contractor's financial trouble as a reason to check it immediately.
  • Preserving a lien by registering it on title is only step one. It must also be perfected by starting a court action and registering a certificate of action within a further deadline, or the lien right lapses even after it was properly preserved.
  • The holdback that owners and contractors are required to retain on every project exists specifically to protect subcontractors. It is also finite, so when several trades are owed money on the same project, coordinating a claim against that holdback usually produces a better outcome than each trade acting alone.
  • A missed direct contract with the property owner does not end a subcontractor's options. Construction lien rights exist precisely because subcontractors often have no contract with the owner and still need a way to secure payment against the property itself.
  • When a general contractor goes quiet on payments, waiting to see if it resolves itself is the single riskiest choice. Lien deadlines do not pause for a contractor's excuses, and every week of delay narrows what is left in the holdback for everyone still owed money.
This case study is entirely fictional. It does not describe any real client, file, or matter handled by Treadstone Law, and it is not a real file with details changed. All names, people, properties, businesses, dollar amounts, dates, and events are invented, and any resemblance to a real person, business, or situation is coincidental. Fictional scenarios like this one illustrate the kinds of legal issues people in Ontario commonly face and how a lawyer can help. They are general information, not legal advice — no two matters unfold the same way, and nothing here predicts the outcome of any real case. Reading a case study does not create a lawyer-client relationship. If you are facing something similar, speak with a lawyer about your specific circumstances.

This is a litigation problem we handle

Start a file online — flat, published fees, reviewed by a licensed lawyer before a dollar is owed.

ContactStart a File →