The situation
Amalia worked full-time as an air traffic controller, and Fernanda was a police sergeant. On the side, the two had built a small business supplying commercial refrigeration and kitchen equipment to restaurants and catering operations across the Greater Toronto Area, sourcing units from manufacturers and handling installation for buyers who did not want to deal directly overseas. It had grown steadily over several years into a business that, in a good year, brought in revenue well beyond either of their salaries.
Their largest order to date came from Pratheep, who ran a mid-sized catering company based in Vaughan and was expanding into a second commercial kitchen. Pratheep signed a written supply agreement for a custom package of walk-in coolers, freezers, and prep equipment priced at roughly $620,000, paid a deposit, and scheduled delivery and installation over several weeks. Buried in the agreement's boilerplate, on a page neither Amalia nor Fernanda had focused on when the deal was under time pressure, was a clause stating that any dispute arising out of the agreement would be resolved by private arbitration rather than through the courts.
The dispute that followed
Delivery and installation went ahead, but Pratheep stopped paying partway through the schedule, claiming several of the units were undersized for the new kitchen and that installation delays had cost the catering business money during a busy season. Amalia and Fernanda disputed both claims: the equipment matched the specifications Pratheep's own kitchen designer had signed off on, and the delays, in their view, traced back to site readiness issues on Pratheep's end. Roughly $370,000 of the contract price remained unpaid.
After months of unanswered invoices and stalled conversations, Amalia and Fernanda came to Treadstone Law wanting to sue in the Superior Court, where they expected a judge, a public docket, and a process they understood at least in broad strokes. A statement of claim was issued setting out the unpaid balance. Pratheep's lawyer responded not with a defence on the merits, but with a motion to stay the court proceeding and compel arbitration, pointing to the clause in the supply agreement.
Amalia and Fernanda objected on several grounds: the clause had never been discussed or negotiated, it sat deep in a document drafted mostly around delivery logistics rather than dispute resolution, and arbitration meant paying for a private arbitrator on top of legal costs, an expense that felt disproportionate for what was, to them, a straightforward payment dispute. They wanted their day in a courtroom, not a private process that felt like it favoured whichever side could better absorb the cost of a drawn-out proceeding.
What we did
- Assessed the clause honestly before the motion was heard. Ontario's Arbitration Act, 1991 generally requires a court to stay litigation and send parties to arbitration where a valid clause covers the dispute, subject to narrow exceptions. We reviewed the supply agreement's wording, confirmed both parties had signed it as the operative contract for the transaction, and gave Amalia and Fernanda a candid assessment: the clause was broadly worded and likely enforceable, even though it had not been the focus of negotiations.
- Argued the exceptions that were genuinely available. We still opposed the stay, raising the arguments with real legal footing: that the clause's placement and lack of discussion bore on whether it was properly incorporated into the deal, and that resolving a straightforward payment dispute through arbitration created cost that was disproportionate to what was really a debt collection matter. We were clear that these were reasonable arguments to make, not guaranteed winners.
- Prepared for both outcomes at once. Rather than betting everything on defeating the stay motion, we began lining up the evidence the claim would need regardless of forum: the signed specifications, delivery records, installation logs, and the correspondence showing which delays were attributable to which side. That work was never wasted, whichever way the motion went.
- Advised on the real trade-off once the ruling came down. The Superior Court granted the stay, finding the clause valid and the dispute squarely within its scope. Once litigation was off the table, we walked Amalia and Fernanda through what arbitration would actually involve: selecting or agreeing on an arbitrator, splitting that arbitrator's fees, and running a private process on a faster timeline than a typical court claim, but without a public record and without the same automatic right of appeal.
- Moved directly into the arbitration process. We helped select an arbitrator experienced in commercial supply disputes, exchanged the specification and delivery documentation with Pratheep's side, and built the claim around the gap between what was contracted for and what was actually delivered, while responding to Pratheep's delay and sizing allegations point by point.
- Pushed for a settlement conference before a full hearing. Once both sides had exchanged their evidence and it was clear neither claim was a clean sweep, we proposed resolving the dispute through a negotiated settlement mid-arbitration rather than running a multi-day hearing that would add further shared arbitrator costs on top of what had already been spent.
The outcome
The forum fight was a loss on its own terms. The court held that Amalia and Fernanda's own supply agreement bound them to arbitration, rejecting the argument that the clause's placement in the document or its absence from active negotiation made it unenforceable. Boilerplate clauses, signed by both sides as part of the operative contract, are generally treated as binding whether or not either party gave that specific page much attention at the time.
The underlying money dispute told a more mixed story. Amalia and Fernanda's evidence held up well on the specification claim: the equipment matched what Pratheep's own kitchen designer had approved, and Pratheep's expert struggled to establish otherwise. But the installation delay evidence cut both ways, with site readiness problems on Pratheep's end and some scheduling slippage on the supply side each contributing to the overrun. Rather than let an arbitrator decide that split down the middle after a full hearing, both sides agreed to a settlement conference partway through the process.
Pratheep agreed to pay roughly $310,000 of the outstanding $370,000, accounting for a partial credit tied to the delay dispute, with the arbitrator's fees split evenly between the parties as the supply agreement required. Amalia and Fernanda recovered the large majority of what they were owed, but not all of it, and they did so through a private process they had specifically tried to avoid. The claim was resolved roughly nine months after the original court action was filed, most of that time spent inside arbitration rather than in front of a judge.
For Amalia and Fernanda, the experience reshaped how they thought about the paperwork side of the business. They had always treated the supply agreement as a formality to get signed quickly so installation could begin, focusing their attention on specifications, pricing, and delivery dates rather than the dispute resolution clause sitting near the end of the document. After this dispute, they began having every new template contract reviewed before it went out to buyers, specifically checking how disputes would be resolved and who would pay for that process, so the next disagreement would not come with an unwelcome forum surprise attached.
What you can learn from this
- An arbitration clause buried in the boilerplate of a signed contract is usually still enforceable. Courts do not require that both sides discussed or negotiated every clause for it to bind them.
- If your business regularly signs supply, service, or delivery contracts, read the dispute resolution section before you sign, not after a dispute arises. Once litigation is underway, it is too late to bargain for a different forum.
- Fighting an arbitration clause you dislike is sometimes worth attempting, but go in with a realistic sense of the odds, and prepare your underlying evidence in parallel so that time is never wasted regardless of which forum decides the case.
- Arbitration is faster and more private than litigation, but it is not free. The parties typically split the arbitrator's fees, which becomes part of the cost-benefit calculation once a mid-process settlement is on the table.
- A partial recovery secured through a negotiated settlement, reached without the added cost of a full hearing, is often a better outcome than pushing every disputed point to a final decision.
This is a litigation problem we handle
Start a file online — flat, published fees, reviewed by a licensed lawyer before a dollar is owed.