- A registered construction lien can be vacated by paying money into court or posting security, which can be done without notice.
- A lien generally expires unless preserved within 60 days, and a preserved lien expires unless perfected within 90 days.
- Whether you need a later closing date depends on how quickly the lien can be vacated and what your buyer and their lawyer will accept.
You thought closing was on track. Then a search of title shows a contractor has registered a construction lien against your home. Your first worry is probably whether the sale can still close on time, or whether you now need to ask for more time.
A lien is not always a reason to delay. In Ontario, the Construction Act gives property owners a way to clear a registered lien by putting up money. This article explains how that works, how long liens last, and what it means for your closing timeline.
What a construction lien is and why it shows up before closing
A construction lien is a claim registered on title by someone who says they are owed money for work or materials supplied to your property. A buyer's lawyer will usually search title before closing, so a lien that was registered recently can surface at the last minute.
Behind many liens is a payment dispute with a contractor or subcontractor. Every payer under a contract or subcontract on which a lien may arise must keep a holdback of 10 per cent. Disagreements about that holdback, or about whether work was finished or paid for, are a common source of claims.
A buyer will generally not want to close with an unresolved lien on the title they are about to receive. That is why the timing question matters to you as the seller.
Vacating the lien by paying money into court or posting security
You do not necessarily have to resolve the underlying dispute before closing. Anyone can get an order vacating a registered lien, without notice, by paying money into court or posting security.
The amount is the full amount claimed plus security for costs, which is the lesser of $250,000 or 25 per cent of the amount claimed. The court may instead accept an amount it considers reasonable.
- You will need funds or acceptable security available, so talk to your lawyer early about where they would come from.
- Ask your lawyer how the court order is obtained, because the buyer's lawyer will want to see the lien dealt with before closing.
How long a lien lasts: the 60-day and 90-day periods
A contractor's lien does not stay on title forever if nothing is done. It generally expires unless it is preserved within 60 days, and that period runs from the earliest of the events listed in s. 31(2), such as the contract being completed, abandoned or terminated.
A preserved lien also expires unless it is perfected within 90 days.
| Stage | Period | What happens if missed |
|---|---|---|
| Preserving the lien | 60 days from the earliest listed event | The lien generally expires |
| Perfecting a preserved lien | 90 days | The preserved lien expires |
These periods do not usually help you clear a lien before a closing that is days away. Waiting for a lien to expire is rarely a practical plan on a tight timeline, and a lawyer can confirm whether the contractor's dates were met.
What this means for your closing date
If you can vacate the lien by paying into court or posting security before closing, you may be able to keep your closing date.
- Tell your lawyer the moment you learn of the lien, so the court step can start right away.
- Be open with the buyer's side. A prompt plan to clear title is more likely to earn patience than silence.
- Expect that any delay can affect other parties in the chain, so ask your lawyer how much time you realistically need.
- Whether the buyer must accept a delay, or may refuse to close, depends on the wording of your Agreement of Purchase and Sale.
If you are selling to someone who may count as a home buyer, the Construction Act treats that person differently from an owner. Under the Construction Act a home buyer is not an owner, which applies where no more than 30% of the price is paid before conveyance and the home is not conveyed until ready for occupancy. How this applies depends on your situation, so it is worth confirming with a lawyer.
What to do next
- Get a copy of the registered lien and note the amount claimed.
- Gather your contract, invoices, payment records and any correspondence with the contractor.
- Ask your lawyer whether to vacate the lien by paying into court or posting security.
- Confirm with your lawyer how much time the process will take before deciding whether to request a later closing date.
- Keep your agent and the buyer's side updated so that any request for a delay is made early and clearly.
Because the right approach depends on your agreement, the amount claimed and your finances, a real estate lawyer can confirm your options before closing.
Frequently asked questions
Can I close on time if there is a lien on title?
Possibly. If the lien is vacated by paying into court or posting security, it can come off title without notice to the other side. Whether that can happen before your closing date depends on how fast you can arrange the money or security.
How much would I have to pay in to vacate a lien?
The amount is the full amount claimed plus security for costs, which is the lesser of $250,000 or 25 per cent of that amount. The court may instead accept an amount it considers reasonable.
Will the lien just expire if I wait?
A lien generally expires unless preserved within 60 days, and a preserved lien expires unless perfected within 90 days. Whether those deadlines were met depends on the dates involved, and it is unlikely to solve a closing that is only days away.
Does vacating the lien end the contractor's claim?
Not necessarily. Vacating the lien clears title, but the contractor's payment claim may still need to be settled or decided. A lawyer can explain what happens to the money or security you put up.
Sources
- Construction Act (e-Laws) — Ontario e-Laws
Links go to official government, court and regulator pages. The law changes — confirm you are reading the current version.
This is a real estate question
Start a file online — flat, published fees, reviewed by a licensed lawyer before a dollar is owed.