The short version
- The Queen's Bridge, which carries Queens Avenue over the Thames River, is fully closed to vehicles from Wednesday, Dec. 2, to Monday, Dec. 7.
- Pedestrians keep full access across the bridge, and LTC buses detour around the work area.
- The City expects the bridge to fully reopen in spring 2027.
The bridge closes to vehicles for five days
LONDON — The City of London said it will fully close the Queen's Bridge to vehicle traffic from Wednesday, December 2, to Monday, December 7.
The City said crews are pouring the new concrete bridge deck, and the closure allows for proper curing of the concrete.
The City said the closure will affect people travelling out of downtown, including those visiting over the weekend of December 5 and 6.
Sources: The Queen's Bridge rehabilitation nearing completion, City of London (london.ca)
Walkers keep access and buses detour
According to the City, pedestrians will keep full access across the bridge throughout the closure. LTC buses will detour around the work area.
The City pointed riders to the London Transit Commission website for the latest bus schedules and detour information. It also published a map of the closure and the vehicle detour.
Sources: The Queen's Bridge rehabilitation nearing completion, City of London (london.ca)
Where the project stands
Construction began in spring 2026. The City said crews have finished work on the north side of the bridge and are continuing rehabilitation on the south side, while keeping at least one lane open to traffic.
Once the deck is poured, the north side is to reopen to traffic and the south side will stay closed for the remaining work, the City said. Work will continue through the winter as weather allows.
The City listed work still to come: concrete walls and road connections, waterproofing the deck and paving. Crews are also replacing the staircases to the Thames Valley Parkway, restoring the pathway beneath the bridge and repairing the east riverbank to help prevent erosion, with that work expected to finish in spring 2027.
Sources: The Queen's Bridge rehabilitation nearing completion, City of London (london.ca)
Where to follow updates
The City said people can follow the Queen's Bridge Rehabilitation project page on its Get Involved website to receive email updates on construction progress, upcoming work and closures. It also pointed to the Renew London construction map, which shows projects across the city.
Sources: The Queen's Bridge rehabilitation nearing completion, City of London (london.ca)
The City said the bridge is expected to fully reopen to traffic in spring 2027, with work continuing through the winter as weather allows.