Leaking Pipes in a New Ontario Condo: Builder Warranty or Corporation?

Found a leak in a new condo? Learn how the corporation's role differs from the builder's Tarion warranty in Ontario, and which dates matter.

Real Estate4 min readTSLBy the Treadstone Law Team · OntarioUpdated November 22, 2026
← All articles
Key takeaways
  • The corporation repairs damage to the standard unit as its governing documents define it, and owners repair everything outside that definition.
  • A builder's warranty is a separate matter from the corporation's duties, and how it applies to defects in your unit depends on your situation, so it is worth confirming with a lawyer.
  • For a delayed occupancy claim, you make the claim to the builder within 180 days of the occupancy date or termination date, and if the builder does not pay, you can claim to Tarion during the first year of possession, or up to 365 days after terminating.

You bought a brand-new unit, and within the first years water appears under the sink, on the ceiling, or in a neighbour's unit. The first instinct is to call the condo office. But in a new building there may be two very different places to turn: the corporation and the builder.

This page helps you sort out which door to knock on first for a plumbing problem, what the corporation does handle, and why you should check the builder-warranty paperwork and its time limits early rather than late.

Start with who owns the pipe

Condo plumbing problems turn on where the failed part sits and what the building's governing documents say about it. Ontario condos are governed in this order: the Condo Act, then the declaration, then the by-laws, then the rules. If they conflict, the Act takes priority.

The corporation repairs damage to the standard unit as defined in its governing documents, and owners must repair everything outside that definition, however the damage was caused.

So a first practical step is to read the declaration's standard unit definition. It tells you whether a particular pipe, fixture or finish is the corporation's job or yours.

What the corporation does and does not do

The corporation's reserve fund may be used only for major repair and replacement of the common elements and assets of the corporation. It is not a general fund for fixing defects inside your unit.

The corporation's property insurance also does not cover improvements or non-standard elements of units. Fixtures, furnishings, equipment and personal property are generally not part of a standard unit.

None of this decides whether the builder owes you a repair under its warranty. That is a separate question, and the corporation's role does not replace it.

Where the builder's Tarion warranty fits

A new-condo purchase comes with the Tarion Addendum, which sets out rights and dates tied to your agreement. Whether a particular leak or plumbing defect is covered, and the time limit to report it, depends on the warranty rules and the documents attached to your own purchase agreement. A lawyer can read those documents against your facts and confirm.

It helps to know which Tarion deadlines are about something else. The dates below belong to delayed occupancy claims, not to defects, so they are shown only so you do not mix them up.

Delayed occupancy itemRule
Claim to the builderWithin 180 days of the occupancy date or termination date
Claim to Tarion if the builder does not payDuring the first year of possession, or up to 365 days after terminating
Buyer's window to terminate after the Outside Occupancy Date30 days

Treat defect deadlines as a separate matter and ask early rather than assume you have the same time.

Protect your position while you sort it out

Water damage can spread quickly, so deal with the emergency first, then build a record. Good records help whether the answer ends up being the corporation, the builder or your own insurer.

If you rent out the unit or a tenant is involved, remember that tenants are not legally required to carry tenant insurance unless the tenancy agreement or the corporation's governing documents require it.

What to do next

Frequently asked questions

Does the condo corporation fix a plumbing leak in my new unit?

It depends on whether the damaged part falls within the standard unit as defined in the corporation's governing documents. The corporation repairs damage to the standard unit, and owners repair everything outside that definition.

Can the corporation use the reserve fund for my unit's defects?

Generally no. The reserve fund may be used only for major repair and replacement of the common elements and assets of the corporation.

Are the 180-day and 365-day Tarion dates deadlines for plumbing defects?

No. Those periods are given for delayed occupancy claims. Defect timelines depend on the warranty documents tied to your purchase, so confirm them with a lawyer.

What if the leak came from a neighbour's unit?

If an owner, tenant or resident caused the damage, the corporation can charge that owner the lesser of the repair cost or its insurance deductible. Some by-laws extend deductible charges further.

Sources

Links go to official government, court and regulator pages. The law changes — confirm you are reading the current version.

This article is general information, not legal advice. Reading it does not create a lawyer-client relationship. Ontario laws, tax rates, and government programs change, and how the law applies depends on your specific facts. For advice about your situation, speak with a licensed Ontario lawyer. Treadstone Law is licensed by the Law Society of Ontario — reach us at 1-844-900-1070 or start a file online.

This is a real estate question

Start a file online — flat, published fees, reviewed by a licensed lawyer before a dollar is owed.

ContactStart a File →