- Give written notice with reasonable detail to both the warranty provider and the builder, within a reasonable time after discovering the defect and before coverage expires.
- Coverage runs in stages, so the type of defect and the date your coverage began matter.
- You cannot be required to pay a deductible or sign a release for covered repairs.
You have found a defect in your new home, such as a leak, a failing window or a crack that worries you. You want to know what to do first, how quickly you must act, and where you stand if the warranty provider says no.
This page walks through the claim process in order. Your own warranty documents and the facts of your defect decide the outcome, so use this as a guide for asking the right questions.
This article covers the law of British Columbia.
Step 1: Confirm what coverage you have
A person may not build a new home unless it is registered for home warranty insurance covering at least 2 years for materials and labour, at least 5 years for the building envelope, including water penetration, and at least 10 years for structural defects. Find your warranty certificate or policy and note the start date of coverage, the provider and the builder's contact details.
Owner builders building for personal use under an authorization need not obtain warranty insurance. If that is your situation, the process below may not apply.
Step 2: Match the defect to the right coverage
| Coverage | What it generally covers |
|---|---|
| Materials and labour, first stage | 12 months for defects in materials and labour and code violations, or 15 months for strata common property |
| Materials and labour, second stage | 24 months for electrical, plumbing and HVAC distribution systems, exterior cladding, caulking, windows and doors that could cause detachment or material damage, and defects making the home unfit to live in |
| Building envelope | Defects including water penetration that causes or is likely to cause material damage, for 5 years |
| Structural | A defect in materials and labour that results in failure of a load-bearing part, or structural damage that materially and adversely affects residential use, for 10 years |
Some items are commonly excluded, including landscaping, roads, site grading, municipal services and septic systems. Defects from normal wear, normal shrinkage, owner-supplied materials, owner or third-party damage, failure to mitigate, acts of nature and post-occupancy alterations can also be excluded. Driveways, walkways, amenity facilities and parking structures in multi-unit buildings cannot be excluded.
Step 3: Give written notice on time
To claim, give written notice with reasonable detail to both the warranty provider and the builder, within a reasonable time after discovering the defect and before coverage expires. No fixed number of days applies to that wording, so do not wait. Delay can create arguments about whether you acted reasonably or let the damage worsen.
- Write a dated letter or email describing the defect, its location and when you found it
- Send it to both the provider and the builder, and keep proof of delivery
- Attach photographs, videos and any inspection reports
- Take reasonable steps to limit further damage, and keep receipts
- Keep a log of every call, visit and reply
Costs, limits and releases
Owners cannot be required to pay a deductible or sign a release for covered repairs. Where a provider sets a minimum claim limit, it is the lesser of the purchase price or $200,000 for a fee simple dwelling, or the lesser of the purchase price or $100,000 for a strata or multi-unit dwelling unit. For common property, it is the least of the total original purchase price, $100,000 times the number of units, or $2,500,000. Providers' policies can be broader than the minimums, so read yours.
If the claim is denied
A denial is not always the end. Ask for the reasons in writing and compare them with your policy, the defect's category and the exclusions above. Common grounds include a missed notice, an excluded item or a dispute over cause, and each can be tested against the evidence you gathered.
The right path after a denial depends on your policy and the facts, so a lawyer can confirm your options. A lawyer can also tell you about other claims that may exist, such as against the builder. If you were told something untrue in a presale disclosure statement, you may have a separate damages claim, which must start within 2 years after you first learned of the misrepresentation.
What to do next
- Locate your warranty documents and note the coverage start date
- Document the defect today with photos and a written description
- Send written notice to both the provider and the builder
- Keep copies of everything and note every deadline
- Get legal advice early if the claim is delayed or denied
Frequently asked questions
How long do I have to give notice of a defect?
You must give written notice within a reasonable time after discovering the defect and before coverage expires. Because no fixed number of days applies, give notice as soon as you can.
Who do I send the notice to?
Send written notice with reasonable detail to both the warranty provider and the builder. Keep proof that each received it.
Can the provider make me pay a deductible?
Owners cannot be required to pay a deductible or sign a release for covered repairs.
What if my claim is denied?
Ask for the reasons in writing and compare them with your policy and the exclusions. A lawyer can confirm what options your situation allows.
Sources
- Real Estate Development Marketing Act (BC Laws) — bclaws.gov.bc.ca
- Homeowner Protection Act (BC Laws) — bclaws.gov.bc.ca
- Homeowner Protection Act Regulation (BC Laws) — bclaws.gov.bc.ca