- As a payer under a contract on which a lien may arise, you must keep a 10 per cent holdback.
- Anyone, not only the owner, can get an order vacating a registered lien by paying into court or posting security.
- The 60-day and 90-day clocks affect how long the lien can stay a problem for you.
You are the general contractor. A subcontractor or supplier you have not paid in full has registered a lien against your client's home. Your client is upset, and the dispute may land on you.
This page looks at the situation from your side: your holdback duty as a payer, your ability to clear the lien, and how the lien deadlines affect your position.
Your duty as a payer
Under the Construction Act, every payer under a contract or subcontract on which a lien may arise must keep a holdback of 10 per cent. As a general contractor paying your subcontractors, you are a payer. The holdback duty is not only your client's.
In plain words, a holdback is a portion of the money owed that is kept back instead of being paid out right away. Keeping track of it is part of running a job where liens are possible.
If a subcontractor lien has been registered, check your own records of what you have held back and what you have paid. Those records will matter in any discussion with your client and the lien claimant.
You do not have to be the owner to clear the lien
Anyone can get an order vacating a registered lien, without notice, by paying into court or posting security. That includes you as the contractor. The amount is the full amount claimed plus the lesser of $250,000 or 25 per cent of that amount as security for costs.
The court may instead accept an amount it considers reasonable. Clearing the lien this way can relieve pressure on your client, but it also means you put up money or security, so it is worth getting legal advice first.
Vacating a lien means the registered lien is removed through a court order. It does not by itself settle whether the subcontractor is owed the money, so you will still want a plan for the underlying payment dispute.
How the 60 and 90 day clocks affect you
A contractor's lien generally expires unless preserved within 60 days, counted from the earliest of the events listed in s. 31(2), such as the contract being completed, abandoned or terminated. A preserved lien also expires unless perfected within 90 days.
- If the claimant missed the 60-day window, the lien may not have been properly preserved.
- If it was preserved but not perfected within 90 days, it may expire.
- Which dates apply depends on the facts, so have them checked before you rely on them.
Because the starting point depends on which event happened first, gather your completion, termination and payment records early. A lawyer can help you work out the dates that apply to your job.
When your client may be a home buyer
Under the Construction Act, a home buyer is not an owner. A home buyer is someone who buys an owner's interest in a home where no more than 30% of the price is paid before conveyance and the home is not conveyed until ready for occupancy.
If your client bought an interest in a home rather than hiring you to work on a home they already own, ask whether that description fits. Whether it does depends on the facts of the purchase, including how much of the price was paid before conveyance and when the home was conveyed, so it is worth confirming with a lawyer.
Your options at a glance
| Option | What to know |
|---|---|
| Pay the subcontractor | May resolve the dispute; check what you owe and what holdback you kept. |
| Vacate the lien | Pay into court or post security. |
| Check the deadlines | Review preservation and perfection timing. |
What to do next
- Get a copy of the registered lien and note the amount claimed.
- Review your contract, invoices, payments and holdback records.
- Work out the dates: when the contract was completed, abandoned or terminated.
- Talk with your client about the plan before anyone acts.
- Speak with a construction lawyer about paying, vacating or disputing the lien.
Frequently asked questions
Do I have to hold back 10 per cent as a general contractor?
Every payer under a contract or subcontract on which a lien may arise must keep a 10 per cent holdback. As a contractor paying subcontractors, you are generally in that position.
Can I vacate a lien on my client's home?
Anyone can get an order vacating a registered lien by paying into court or posting security. The amount is set by the Act, though the court may accept a reasonable amount instead.
What are the 60 and 90 day periods?
A lien generally expires unless preserved within 60 days, and a preserved lien expires unless perfected within 90 days. The 60 days runs from the earliest of the events listed in s. 31(2).
Should I speak to a lawyer before posting security?
Yes, it is wise. Posting money or security has costs for you, and the right approach depends on the dates, the contract and the amount claimed.
Sources
- Construction Act (e-Laws) — Ontario e-Laws
Links go to official government, court and regulator pages. The law changes — confirm you are reading the current version.
This is a real estate question
Start a file online — flat, published fees, reviewed by a licensed lawyer before a dollar is owed.